Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | NCC Ltd. | 20024895 | PALHAVAPUR | 218.78 | 192.48 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 19 | 19 | Yes | 0 | NA | No | 10284.00 | 8794.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Belghat | Paharpur | 456991 | Palahwapur | 148 | 148 | 100 | Har Gar Jal | Not Certified |
| 2 | Gorakhpur | Belghat | Paharpur | 456993 | Rajjupur | 9 | 9 | 100 | Har Gar Jal | Not Certified |
| 3 | Gorakhpur | Belghat | Paharpur | 456994 | Mahuadar | 69 | 69 | 100 | Har Gar Jal | Not Certified |
| 4 | Gorakhpur | Belghat | Paharpur | 456995 | Dihwar Khurd | 35 | 35 | 100 | Har Gar Jal | Not Certified |
| 5 | Gorakhpur | Belghat | Paharpur | 456997 | Chitauni Buzurg | 4 | 4 | 100 | Har Gar Jal | Not Certified |
| 6 | Gorakhpur | Belghat | Paharpur | 703581 | Alavlpur | 137 | 0 | 0 | Work In Progress | Not Certified |