Scheme Details
DISTRICT
Gorakhpur
AGENCY
NCC Ltd.
SCHEME ID
20024940
SCHEME NAME
Totaha Urf Bhauwapar
ESTIMATED COST
534.13
EXPENDITURE
303.15
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16354.00
Meter
Length Laid
15532.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Piprauli | Totaaha Urfbhauwapar | 455236 | Totaaha Urfbhauwapar | 1056 | 1056 | 100% | Har Ghar Jal | Not Certified |
| 2 | Gorakhpur | Piprauli | Totaaha Urfbhauwapar | 455237 | Arazibanshi Jaiswal | 73 | 73 | 100% | Har Ghar Jal | Not Certified |
| 3 | Gorakhpur | Piprauli | Totaaha Urfbhauwapar | 455238 | Shiv Chak | 48 | 48 | 100% | Har Ghar Jal | Not Certified |
| 4 | Gorakhpur | Piprauli | Totaaha Urfbhauwapar | 455239 | Jot Sikari | 20 | 4 | 20% | Work In Progress | Not Certified |