Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | NCC Ltd. | 20024956 | Girdharpur Dubey & Pandaypar | 555.67 | 303.38 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 30 | 30 | Yes | 0 | NA | No | 17564.00 | 16000.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Kauriram | Girdharpur Dubauliya | 456343 | Girdharpur Dubauliya | 134 | 98 | 73 | Work In Progress | Not Certified | 
| 2 | Gorakhpur | Kauriram | Girdharpur Dubauliya | 456344 | Girdharpur Chaubey | 109 | 72 | 66 | Work In Progress | Not Certified | 
| 3 | Gorakhpur | Kauriram | Girdharpur Dubauliya | 456345 | Deodar Gopalpur | 21 | 21 | 100 | Har Gar Jal | Not Certified | 
| 4 | Gorakhpur | Kauriram | Girdharpur Dubauliya | 456346 | Kauaram Khurd | 67 | 67 | 100 | Har Gar Jal | Not Certified | 
| 5 | Gorakhpur | Kauriram | Girdharpur Dubauliya | 456347 | Chari | 45 | 1 | 2 | Work In Progress | Not Certified | 
| 6 | Gorakhpur | Kauriram | Pandeypar | 456396 | Pandeypar | 522 | 521 | 100 | Work In Progress | Not Certified |