Scheme Details
DISTRICT
Gorakhpur
AGENCY
NCC Ltd.
SCHEME ID
20024956
SCHEME NAME
Girdharpur Dubey & Pandaypar
ESTIMATED COST
555.67
EXPENDITURE
501.15
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17564.00
Meter
Length Laid
16000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Kauriram | Girdharpur Dubauliya | 456343 | Girdharpur Dubauliya | 134 | 98 | 73% | Work In Progress | Not Certified |
| 2 | Gorakhpur | Kauriram | Girdharpur Dubauliya | 456344 | Girdharpur Chaubey | 109 | 72 | 66% | Work In Progress | Not Certified |
| 3 | Gorakhpur | Kauriram | Girdharpur Dubauliya | 456345 | Deodar Gopalpur | 21 | 21 | 100% | Har Ghar Jal | Not Certified |
| 4 | Gorakhpur | Kauriram | Girdharpur Dubauliya | 456346 | Kauaram Khurd | 67 | 67 | 100% | Har Ghar Jal | Not Certified |
| 5 | Gorakhpur | Kauriram | Girdharpur Dubauliya | 456347 | Chari | 45 | 1 | 2% | Work In Progress | Not Certified |
| 6 | Gorakhpur | Kauriram | Pandeypar | 456396 | Pandeypar | 522 | 521 | 100% | Work In Progress | Not Certified |