Scheme Details
DISTRICT Varanasi
AGENCY Larsen & Toubro Ltd
SCHEME ID 20025033
SCHEME NAME Birsinghpur
ESTIMATED COST 249.44
EXPENDITURE 154.63
AUTOMATION STATUS Not Integrated
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 5
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 21
Procured 21 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 10142.00 Meter
Length Laid 10132.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

5 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Varanasi Arajiline Virsinghpur 476350 Virsinghpur 126 126 100% Har Ghar Jal Not Certified
2 Varanasi Arajiline Virsinghpur 476351 Lachirampur 88 79 90% Work In Progress Not Certified
3 Varanasi Arajiline Virsinghpur 476352 Milkypur 132 119 90% Work In Progress Not Certified
4 Varanasi Arajiline Virsinghpur 476353 Barikpur 38 25 66% Work In Progress Not Certified
5 Varanasi Arajiline Virsinghpur 680713 DASHRATHCHAK 103 102 99% Work In Progress Not Certified