Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Sitapur | Larsen & Toubro Ltd | 20025153 | NARAINPUR WATER SUPPLY SCHEME | 218.95 | 108.88 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Sitapur | Gondlamau | Narainpur | 410125 | Bargadiya | 71 | 65 | 92 | Work In Progress | Not Certified | Not Verified |
2 | Sitapur | Gondlamau | Narainpur | 410126 | Khale Korwa | 93 | 83 | 89 | Work In Progress | Not Certified | Verified |
3 | Sitapur | Gondlamau | Narainpur | 410127 | Narainpur | 231 | 231 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Sitapur | Gondlamau | Narainpur | 410128 | Uncha Korhwa | 42 | 23 | 55 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 14 | 14 | Yes | 0 | NA | No | 8424.00 | 8000.00 |