Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Approve By Agency Status Approve By EE Status Automation Status
1 Bulandshahr JMC - Lakshmi (JV) 20025307 Khandoi & Shafinagar WSS 327.56 152.92 Verified Verified Not Integrated

Scheme Assigne Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified Handed Over Villages
1 Bulandshahr Unchagaon Shafi Nagar 393541 Shafi Nagar 337 328 97 Work In Progress Not Certified Not Verified
2 Bulandshahr Unchagaon Khandoi 393542 Khandoi 401 391 98 Work In Progress Not Certified Not Verified

Scheme Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 0 27 27 Yes 0 NA No 14354.00 14000.00