Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Larsen & Toubro Ltd | 20025439 | Jogiveer_Badahra Kot Water Supply Scheme | 463.87 | 151.86 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 35 | 35 | Yes | 0 | NA | No | 19842.00 | 18601.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Utraula | Badahra Kot | 444249 | Badahra Kot | 568 | 567 | 100 | Work In Progress | Not Certified |
| 2 | Balrampur | Utraula | Jogiveer | 444283 | Jogiveer | 207 | 205 | 99 | Work In Progress | Not Certified |