Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Auraiya | GVPR | 20025450 | DHARAMPUR JAHURALI PWS | 394.22 | 235.29 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 13060.00 | 13000.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Achhalda | Purwa Asha | 420453 | Purwa Asha | 210 | 200 | 95 | Work In Progress | Not Certified | 
| 2 | Auraiya | Achhalda | Purwa Asha | 420454 | Chandraua Phaphund | 84 | 73 | 87 | Work In Progress | Not Certified | 
| 3 | Auraiya | Achhalda | Dharampur Jahurali | 420455 | Dharampur Jahurali | 179 | 171 | 96 | Work In Progress | Not Certified | 
| 4 | Auraiya | Achhalda | Dharampur Jahurali | 420457 | Lahroi | 136 | 122 | 90 | Work In Progress | Not Certified |