Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20025579 | Rasulpur Mujaffar Gram Panchayat Water Supply | 288.28 | 230.98 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 8165.00 | 8719.40 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Kotwali | RASULPUR MUJAFFAR | 386603 | Rasulpur Mujaffar | 502 | 497 | 99 | Work In Progress | Not Certified |