Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Auraiya | GVPR | 20025616 | SURAJPUR AIRWA &BEELPUR AIRVA | 389.78 | 290.49 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 13572.00 | 13572.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Airwakatra | Beelpur Airwa | 420199 | Beelpur Airwa | 299 | 299 | 100 | Har Gar Jal | Not Certified | 
| 2 | Auraiya | Airwakatra | Surajpur Airwa | 420200 | Surajpur Airwa | 188 | 188 | 100 | Har Gar Jal | Certified | 
| 3 | Auraiya | Airwakatra | Surajpur Airwa | 420201 | Naunakpur | 11 | 11 | 100 | Har Gar Jal | Certified | 
| 4 | Auraiya | Airwakatra | Surajpur Airwa | 420202 | Nagla Hariram | 128 | 128 | 100 | Har Gar Jal | Certified |