Scheme Details
DISTRICT
Gonda
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20025894
SCHEME NAME
Phrenda Kanoongo Water Supply Scheme
ESTIMATED COST
275.14
EXPENDITURE
78.52
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
18
Procured
18
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13203.00
Meter
Length Laid
13203.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Itia Thok | PHRENDA KANOONGO | 444657 | JANKORA | 143 | 132 | 92% | Work In Progress | Not Certified |
| 2 | Gonda | Itia Thok | PHRENDA KANOONGO | 444658 | Phrenda Kanoongo | 253 | 244 | 96% | Work In Progress | Not Certified |