Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Varanasi | Larsen & Toubro Ltd | 20025910 | DHADORPUR | 347.01 | 204.97 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Varanasi | Arajiline | Dhadorpur | 476346 | Dhadorpur | 320 | 283 | 88 | Work In Progress | Not Certified | Verified |
2 | Varanasi | Arajiline | Dhadorpur | 476347 | Khamaipur | 134 | 127 | 95 | Work In Progress | Not Certified | Verified |
3 | Varanasi | Arajiline | Dhadorpur | 476348 | Tariya | 106 | 105 | 99 | Work In Progress | Not Certified | Verified |
4 | Varanasi | Arajiline | Dhadorpur | 476349 | Tin Karava | 87 | 87 | 100 | Har Gar Jal | Not Certified | Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 28 | 28 | No | 0 | NA | No | 15330.00 | 15330.00 |