Scheme Details
DISTRICT
Bijnor
AGENCY
LC INFRA
SCHEME ID
20026226
SCHEME NAME
Bagaina Village Water Supply
ESTIMATED COST
203.68
EXPENDITURE
189.96
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
3841.00
Meter
Length Laid
4100.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Mo. Purdewal | Bagaina | 386085 | Bagaina | 335 | 335 | 100% | Har Ghar Jal | Certified |
| 2 | Bijnor | Mo. Purdewal | Bagaina | 386086 | Mukeempur Balu | 285 | 285 | 100% | Har Ghar Jal | Certified |