Scheme Details
DISTRICT Jaunpur
AGENCY AFCONS
SCHEME ID 20026294
SCHEME NAME Hardwari Water Supply Scheme
ESTIMATED COST 368.85
EXPENDITURE 213.89
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 5
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 26647.00 Meter
Length Laid 21206.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

5 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Jaunpur Barsathi Hardwari 469875 Koraha 77 49 64% Work In Progress Not Certified
2 Jaunpur Barsathi Hardwari 469876 Shekhanpur 68 41 60% Work In Progress Not Certified
3 Jaunpur Barsathi Hardwari 469877 Ramchandarpur 23 16 70% Work In Progress Not Certified
4 Jaunpur Barsathi Hardwari 469878 Hardwari 326 276 85% Work In Progress Not Certified
5 Jaunpur Barsathi Hardwari 469879 Bhatkaiya 42 31 74% Work In Progress Not Certified