Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Megha | 20026340 | KODARA BHUWAL PATTI | 180.46 | 110.59 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 13 | 13 | Yes | 0 | NA | No | 8568.00 | 5750.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Nathnagar | Kodara Bhual Patti | 452796 | Kodara Bhual Patti | 104 | 104 | 100 | Har Gar Jal | Not Certified |
| 2 | Sant Kabeer Nagar | Nathnagar | Kodara Bhual Patti | 452797 | Jamuni Khurd | 43 | 43 | 100 | Har Gar Jal | Not Certified |
| 3 | Sant Kabeer Nagar | Nathnagar | Kodara Bhual Patti | 452798 | Devapar | 37 | 37 | 100 | Har Gar Jal | Not Certified |