Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Etawah | Indian Hume Pipe | 20026404 | Manikpur Bhikhan PWS | 281.56 | 145.88 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 10563.00 | 6275.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Basrehar | Keshonpur Kalan | 419737 | Keshonpur Kalan | 246 | 234 | 95 | Work In Progress | Not Certified |
| 2 | Etawah | Basrehar | Keshonpur Kalan | 419738 | Mahtuwa | 173 | 165 | 95 | Work In Progress | Not Certified |
| 3 | Etawah | Basrehar | Keshonpur Kalan | 419739 | Manikpur Bhikhan | 107 | 99 | 93 | Work In Progress | Not Certified |