Scheme Details
DISTRICT
Pratapgarh
AGENCY
Power Mech Projects Ltd
SCHEME ID
20026943
SCHEME NAME
GOBARI GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST
356.39
EXPENDITURE
230.30
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
20894.00
Meter
Length Laid
20894.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Sandwa Chandrika | Gobari | 429622 | Gobari | 510 | 508 | 100% | Work In Progress | Not Certified |