Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Rampur | NKG-PRIMUS (JV) | 20027348 | BOODHPUR GP W/S SCHEME | 190.92 | 74.78 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 16 | Yes | 0 | NA | No | 5732.00 | 5945.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Rampur | Shahabad | Boodpur | 390118 | Boodpur | 211 | 211 | 100 | Har Gar Jal | Not Certified |
| 2 | Rampur | Shahabad | Boodpur | 390119 | Kamalpur | 97 | 97 | 100 | Har Gar Jal | Not Certified |