Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Shravasti
AGENCY Larsen & Toubro Ltd
SCHEME ID 20030083
SCHEME NAME Turahni Balram_Hariharrpur PWS
ESTIMATED COST 335.30
EXPENDITURE 312.93
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 18
Procured 18 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 20389.00 Meter
Length Laid 15150.00 Meter

Scheme Assigned Villages

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Shravasti Gilaula Hariharrpur 443332 Hariharrpur 255 253 99% Work In Progress Not Certified
2 Shravasti Gilaula Hariharrpur 443333 Dhainsra 103 103 100% Har Ghar Jal Not Certified
3 Shravasti Gilaula Hariharrpur 443334 Tikar Aladad 137 135 99% Work In Progress Not Certified
4 Shravasti Gilaula Turhin Balram 443354 Turhin Balram 360 355 99% Work In Progress Not Certified