Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Shravasti | Larsen & Toubro Ltd | 20030441 | MOHRANIYA MV PWS | 441.97 | 209.67 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 35 | 35 | Yes | 0 | NA | No | 14938.00 | 14899.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shravasti | Gilaula | Mohrniya | 443352 | Mohrniya | 594 | 594 | 100 | Har Gar Jal | Not Certified |
| 2 | Shravasti | Gilaula | Mohrniya | 443353 | Sonwan | 210 | 203 | 97 | Work In Progress | Not Certified |