Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | UNIVERSAL MEP | 20030545 | BICHALA GRAM PANCHAYAT WATER SUPPLY SCHEME | 242.60 | 119.95 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 18 | 18 | NA | 0 | NA | No | 8836.00 | 9336.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Rudauli | Bichala | 436361 | Bichala | 233 | 219 | 94 | Work In Progress | Not Certified |
| 2 | Ayodhya | Rudauli | Bichala | 436362 | MANPUR | 311 | 286 | 92 | Work In Progress | Not Certified |