Scheme Details
DISTRICT
Bahraich
AGENCY
PNC-SPML-JV
SCHEME ID
20031367
SCHEME NAME
MASDIHA MAHASI PWS
ESTIMATED COST
347.76
EXPENDITURE
161.95
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10026.00
Meter
Length Laid
10000.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | Mahasi | Masadiha | 442225 | Masadiha | 691 | 691 | 100% | Har Ghar Jal | Not Certified |