Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Bahraich | PNC-SPML-JV | 20031394 | MEERPUR & KONARI KAISARGANJ MVS PWS | 347.79 | 132.49 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 16 | Yes | 0 | NA | No | 16084.00 | 16084.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | Kaisarganj | Meerpur | 442652 | Chilawa | 175 | 133 | 76 | Work In Progress | Not Certified | 
| 2 | Bahraich | Kaisarganj | Meerpur | 442653 | Mirpur | 181 | 166 | 92 | Work In Progress | Not Certified | 
| 3 | Bahraich | Kaisarganj | Konari | 442654 | Konari | 200 | 173 | 86 | Work In Progress | Not Certified | 
| 4 | Bahraich | Kaisarganj | Konari | 442655 | Jamaluddinpur | 100 | 100 | 100 | Har Gar Jal | Not Certified | 
| 5 | Bahraich | Kaisarganj | Konari | 442656 | Firozpur | 53 | 8 | 15 | Work In Progress | Not Certified |