Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20032065
SCHEME NAME
Berkhera Chauhan, Mimla & Kirar Kheri Gram Panchayat Water Supply
ESTIMATED COST
661.19
EXPENDITURE
432.72
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
44
Procured
45
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16626.00
Meter
Length Laid
15952.00
Meter
Scheme Assigned Villages
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Alhepur | Mimla | 387061 | Mimla | 228 | 228 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bijnor | Alhepur | Berkhera Chauhan | 387075 | Berkhera Chauhan | 111 | 111 | 100% | Har Ghar Jal | Not Certified |
| 3 | Bijnor | Alhepur | Berkhera Chauhan | 387076 | Arajigopaljot | 65 | 56 | 86% | Work In Progress | Not Certified |
| 4 | Bijnor | Alhepur | Berkhera Chauhan | 387077 | Mohmad Pur Lal | 39 | 39 | 100% | Har Ghar Jal | Not Certified |
| 5 | Bijnor | Alhepur | Kirar Kheri | 387078 | Kirar Kheri | 265 | 264 | 100% | Work In Progress | Not Certified |
| 6 | Bijnor | Alhepur | Kirar Kheri | 387079 | Kand Kheri | 96 | 96 | 100% | Har Ghar Jal | Not Certified |