Scheme Details
DISTRICT
Pratapgarh
AGENCY
Power Mech Projects Ltd
SCHEME ID
20032573
SCHEME NAME
Dandupur Daulat Gram Panchayat Water Supply Scheme
ESTIMATED COST
327.21
EXPENDITURE
189.35
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
32
Procured
32
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
21440.00
Meter
Length Laid
21080.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Sandwa Chandrika | Dandupur Daulat | 429649 | Dandupur Daulat | 164 | 163 | 99% | Work In Progress | Not Certified |
| 2 | Pratapgarh | Sandwa Chandrika | Dandupur Daulat | 429650 | Nagmalpur | 147 | 146 | 99% | Work In Progress | Not Certified |
| 3 | Pratapgarh | Sandwa Chandrika | Dandupur Daulat | 429651 | Rampur Umari | 117 | 116 | 99% | Work In Progress | Not Certified |