Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | GA INFRA - BABA (JV) | 20033147 | govindpur WATER SUPPLY SCHEME | 283.33 | 158.15 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 21599.00 | 20801.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Atrauliya | Govindpur | 461172 | Itapal | 88 | 23 | 26 | Work In Progress | Not Certified | 
| 2 | Azamgarh | Atrauliya | Govindpur | 461173 | Bhawanipur | 116 | 30 | 26 | Work In Progress | Not Certified | 
| 3 | Azamgarh | Atrauliya | Govindpur | 461174 | Govindpur | 181 | 87 | 48 | Work In Progress | Not Certified |