Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | GA INFRA - BABA (JV) | 20033294 | kari gatamput WATER SUPPLY SCHEME | 376.94 | 178.79 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 30 | 30 | NA | 0 | NA | No | 19892.00 | 18798.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Ahiraula | Kari Ghatamput | 461407 | Kari Ghatamput | 354 | 354 | 100 | Har Gar Jal | Not Certified |
| 2 | Azamgarh | Ahiraula | Kari Ghatamput | 461408 | Shahwanipur | 94 | 94 | 100 | Har Gar Jal | Not Certified |
| 3 | Azamgarh | Ahiraula | Kari Ghatamput | 461409 | Chak Latif | 35 | 35 | 100 | Har Gar Jal | Not Certified |
| 4 | Azamgarh | Ahiraula | Kari Ghatamput | 461488 | Chack Dawoud Shah | 55 | 55 | 100 | Har Gar Jal | Not Certified |