Scheme Details
DISTRICT
Lakhimpur Kheri
AGENCY
NCC Ltd.
SCHEME ID
20033339
SCHEME NAME
KISHUNPUR AJITPUR JJM SCHEME
ESTIMATED COST
249.08
EXPENDITURE
163.22
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8093.00
Meter
Length Laid
5790.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Pasgawan | Kishunpur Ajit | 408755 | Kishunpur Ajit | 130 | 130 | 100% | Har Ghar Jal | Not Certified |
| 2 | Lakhimpur Kheri | Pasgawan | Kishunpur Ajit | 408756 | Mukkadarpur | 67 | 67 | 100% | Har Ghar Jal | Not Certified |
| 3 | Lakhimpur Kheri | Pasgawan | Kishunpur Ajit | 408757 | Ramapur | 99 | 97 | 98% | Work In Progress | Not Certified |
| 4 | Lakhimpur Kheri | Pasgawan | Kishunpur Ajit | 408758 | Talsagar | 50 | 14 | 28% | Work In Progress | Not Certified |