Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | NCC Ltd. | 20033633 | Kaspa Water Supply Scheme | 244.08 | 141.70 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 18 | 18 | Yes | 0 | NA | No | 11768.00 | 11353.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Pisawan | Kapsa | 409589 | Chakroda | 31 | 30 | 97 | Work In Progress | Not Certified | 
| 2 | Sitapur | Pisawan | Kapsa | 409590 | Kapsa | 180 | 179 | 99 | Work In Progress | Not Certified | 
| 3 | Sitapur | Pisawan | Kapsa | 409591 | Makrehra | 106 | 106 | 100 | Har Gar Jal | Not Certified | 
| 4 | Sitapur | Pisawan | Kapsa | 409592 | Pahari | 73 | 70 | 96 | Work In Progress | Not Certified |