Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Etah Power Mech Projects Ltd 20034188 BARAI KALYANPUR 581.28 226.76 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
1 3 3 3 3 1 1 0 60 60 Yes 0 NA No 20595.00 20595.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Etah Awagarh Barai Kalyanpur 399975 Barai Kalyan Pur 869 464 53 Work In Progress Not Certified