Scheme Details
DISTRICT
Kanpur Dehat
AGENCY
Indian Hume Pipe
SCHEME ID
20034284
SCHEME NAME
JALALPUR NAGIN
ESTIMATED COST
402.13
EXPENDITURE
372.08
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
15423.00
Meter
Length Laid
17708.40
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kanpur Dehat | Sarvankheda | Jalalpur Nagin | 421487 | Jalalpur Nagin | 788 | 788 | 100% | Har Ghar Jal | Certified |