Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Ambedkar Nagar
AGENCY Vindhya-GAJA (JV)
SCHEME ID 20034347
SCHEME NAME MAMREJPUR WATER SUPPLY SCHEME
ESTIMATED COST 329.14
EXPENDITURE 281.99
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 20172.00 Meter
Length Laid 15253.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Ambedkar Nagar Tanda Mamrejpur 437672 Khanpur 18 17 94% Work In Progress Not Certified
2 Ambedkar Nagar Tanda Mamrejpur 437673 Bisunpur 149 143 96% Work In Progress Not Certified
3 Ambedkar Nagar Tanda Mamrejpur 437674 Mamrejpur 232 228 98% Work In Progress Not Certified
4 Ambedkar Nagar Tanda Mamrejpur 437675 ODRA 152 152 100% Har Ghar Jal Not Certified