Scheme Details
DISTRICT
Rampur
AGENCY
SPML Infra
SCHEME ID
20034362
SCHEME NAME
BAGI GOBINDPURA NEAR PADAMPUR NAWABNAGAR TAH GP W/S Scheme
ESTIMATED COST
360.81
EXPENDITURE
110.99
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16099.00
Meter
Length Laid
12300.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Rampur | Suar | Bagi | 389414 | NAWAB NAGAR TAH | 10 | 4 | 40% | Work In Progress | Not Certified |
| 2 | Rampur | Suar | Bagi | 389495 | Bagi | 165 | 163 | 99% | Work In Progress | Not Certified |
| 3 | Rampur | Suar | Bagi | 389497 | GOBINDPURA NEAR PADAMPUR | 75 | 74 | 99% | Work In Progress | Not Certified |