Scheme Details
DISTRICT
Bareilly
AGENCY
NCC Ltd.
SCHEME ID
20034978
SCHEME NAME
Mundia Bisan Sahai & Himkara
ESTIMATED COST
364.30
EXPENDITURE
117.92
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
25
Procured
25
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13472.00
Meter
Length Laid
13387.00
Meter
Scheme Assigned Villages
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Nawabganj | Himkara | 403825 | Himkara | 226 | 226 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bareilly | Nawabganj | Himkara | 403826 | Deorania Jagir | 133 | 133 | 100% | Har Ghar Jal | Not Certified |
| 3 | Bareilly | Nawabganj | Mundia Bisan Sahai | 403849 | Mundia Bisan Sahai | 239 | 239 | 100% | Har Ghar Jal | Not Certified |
| 4 | Bareilly | Nawabganj | Mundia Bisan Sahai | 403850 | BIHARIPUR PACHTAUR | 71 | 3 | 4% | Work In Progress | Not Certified |