Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Vindhya-GAJA (JV) | 20035156 | BARAULI AVASHANPUR WSS | 645.54 | 308.29 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 34586.00 | 34586.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Jalalpur | Barauli Avashanpur | 438310 | Barauli Ashanandpur | 412 | 412 | 100 | Har Gar Jal | Not Certified |
| 2 | Ambedkar Nagar | Jalalpur | Bairagal | 438311 | Bairagal | 282 | 257 | 91 | Work In Progress | Not Certified |
| 3 | Ambedkar Nagar | Jalalpur | Bairagal | 438312 | Sikandarpur | 66 | 65 | 98 | Work In Progress | Not Certified |