Scheme Details
DISTRICT
Saharanpur
AGENCY
Gayatri Projects LTD
SCHEME ID
20035317
SCHEME NAME
Khairsal
ESTIMATED COST
206.65
EXPENDITURE
80.84
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4326.00
Meter
Length Laid
4208.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Gangoh | Khair Sal | 384223 | Khair Sal | 484 | 484 | 100% | Har Ghar Jal | Not Certified |