Scheme Details
DISTRICT Etah
AGENCY ION EXCHANGE
SCHEME ID 20035402
SCHEME NAME BERNI
ESTIMATED COST 312.21
EXPENDITURE 87.24
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 10
Transformer Procured NA
Work Status No
Distribution Line
Total Length 10201.00 Meter
Length Laid 14184.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Etah Jalesar Berni 399864 Berni 619 607 98% Work In Progress Not Certified
2 Etah Jalesar Berni 399865 Ramraipur 33 33 100% Har Ghar Jal Not Certified