Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Kanpur Nagar | Vindhya-GAJA (JV) | 20035433 | ARANJ HAMI & NARAIYANPUR SARH GRAM PANCHAYAT WATER SUPPLY SCHEME- multivillage | 348.48 | 284.45 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Kanpur Nagar | Bhitargaon | Aranj Hami | 422606 | Aranj Hami | 242 | 242 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Kanpur Nagar | Bhitargaon | Aranj Hami | 422607 | Aranj Bankat | 30 | 27 | 90 | Work In Progress | Not Certified | Not Verified |
3 | Kanpur Nagar | Bhitargaon | Narainpur Sarh | 422609 | Aranj Rai | 131 | 30 | 23 | Work In Progress | Not Certified | Not Verified |
4 | Kanpur Nagar | Bhitargaon | Narainpur Sarh | 422613 | Narainpur Sarh | 217 | 168 | 77 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 16298.00 | 14873.00 |