Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Welspun Kaveri Infraprojects JV | 20035473 | Gaura Basantpur | 577.72 | 408.55 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 27237.00 | 26833.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Katehari | Gaura Basantpur | 438765 | Kurmi Deeha | 102 | 102 | 100 | Har Gar Jal | Not Certified | 
| 2 | Ambedkar Nagar | Katehari | Gaura Basantpur | 438766 | Gaura Basantpur | 157 | 157 | 100 | Har Gar Jal | Not Certified | 
| 3 | Ambedkar Nagar | Katehari | Lokapur | 438861 | Lokapur | 29 | 28 | 97 | Work In Progress | Not Certified | 
| 4 | Ambedkar Nagar | Katehari | Lokapur | 438862 | Teuga Jalalpur | 257 | 257 | 100 | Har Gar Jal | Not Certified | 
| 5 | Ambedkar Nagar | Katehari | Lokapur | 438863 | Ramdas Patti | 94 | 94 | 100 | Har Gar Jal | Not Certified | 
| 6 | Ambedkar Nagar | Katehari | Ahirauli | 438879 | Ahirauli | 257 | 257 | 100 | Har Gar Jal | Not Certified |