Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bareilly | NCC Ltd. | 20035881 | Gangeypur | 228.08 | 152.84 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 14 | 14 | Yes | 0 | NA | No | 9253.00 | 9235.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Bhuta | Gangeypur | 404166 | Gangeypur | 127 | 127 | 100 | Har Gar Jal | Not Certified |
| 2 | Bareilly | Bhuta | Gangeypur | 404167 | Guhulupura | 119 | 119 | 100 | Har Gar Jal | Not Certified |
| 3 | Bareilly | Bhuta | Gangeypur | 404168 | Naudia Ilaka Bahalia | 4 | 4 | 100 | Har Gar Jal | Not Certified |
| 4 | Bareilly | Bhuta | Gangeypur | 404169 | Gularia Makrandpur | 96 | 96 | 100 | Har Gar Jal | Not Certified |