| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Welspun Kaveri Infraprojects JV | 20036033 | Jagdishpur Nokha | 375.66 | 307.71 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 24130.00 | 23951.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Akbarpur | Jagdishpur Nokha | 438920 | Jagdishpur Nokha | 136 | 136 | 100 | Har Gar Jal | Not Certified |
| 2 | Ambedkar Nagar | Akbarpur | Jagdishpur Nokha | 438921 | Tulsipur | 78 | 78 | 100 | Har Gar Jal | Certified |
| 3 | Ambedkar Nagar | Akbarpur | Jagdishpur Nokha | 438922 | Bhikhupur | 28 | 28 | 100 | Har Gar Jal | Certified |
| 4 | Ambedkar Nagar | Akbarpur | Paharpur Tandwa | 438947 | Paharpur Tandwa | 156 | 146 | 94 | Work In Progress | Not Certified |
| 5 | Ambedkar Nagar | Akbarpur | Mohiddinpur | 438957 | Mohiddinpur | 191 | 191 | 100 | Har Gar Jal | Not Certified |