Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kannauj | GVPR | 20036338 | TIRAHIAPUR & NAZARAPUR GRAMIN PEYJAL YOJNA | 619.68 | 430.09 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 2 | 2 | 2 | 2 | 1 | 1 | 1 | 60 | 60 | Yes | 0 | NA | No | 18556.00 | 18556.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kannauj | Kannauj | Tirhiapur | 419216 | Tirhiapur | 597 | 595 | 100 | Work In Progress | Not Certified |
| 2 | Kannauj | Kannauj | Nazarapur | 419229 | Nazarapur | 292 | 292 | 100 | Har Gar Jal | Certified |
| 3 | Kannauj | Kannauj | Nazarapur | 419230 | Dewapurpatti | 72 | 72 | 100 | Har Gar Jal | Certified |
| 4 | Kannauj | Kannauj | Nazarapur | 419231 | Rajaimauthakurain | 173 | 173 | 100 | Har Gar Jal | Certified |