Scheme Details
DISTRICT
Saharanpur
AGENCY
Gayatri Projects LTD
SCHEME ID
20036409
SCHEME NAME
lkahnauti khurd water supply
ESTIMATED COST
310.31
EXPENDITURE
29.13
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
0
Air Compressor Done
0
O.P. Unit Done
0
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
20
Procured
0
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8305.00
Meter
Length Laid
0.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Punwaraka | Lakhnauti Khurd | 383703 | Lakhnauti Khurd | 494 | 278 | 56% | Work In Progress | Not Certified |
| 2 | Saharanpur | Punwaraka | Lakhnauti Khurd | 383704 | Bishanpur | 114 | 114 | 100% | Har Ghar Jal | Not Certified |