Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Budaun PNC-SPML-JV 20037351 BAURA WATER SUPPLY SCHEME 260.88 150.79 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 1 23 23 Yes 0 NA No 7331.00 6972.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Budaun Samrer Baura 402241 Baura 419 419 100 Har Gar Jal Certified
2 Budaun Samrer Baura 402242 Khanpur Bairagi 123 123 100 Har Gar Jal Certified