Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20037359
SCHEME NAME BIRIA DANDA WATER SUPPLY SCHEME
ESTIMATED COST 296.85
EXPENDITURE 212.53
AUTOMATION STATUS
Disconnected View Live Screen
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 9667.00 Meter
Length Laid 5180.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Mion Biriadanda 402463 Biriadanda Chandpura 387 387 100% Har Ghar Jal Certified
2 Budaun Mion Biriadanda 402464 Chandbarai 140 140 100% Har Ghar Jal Certified