Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20037757 | Bahadur GP wss | 144.32 | 71.41 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 13 | 13 | Yes | 0 | NA | No | 5123.00 | 5010.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Saltaua Gopal Pur | Bahadurpur | 448898 | Sekhui | 50 | 47 | 94 | Work In Progress | Not Certified | 
| 2 | Basti | Saltaua Gopal Pur | Bahadurpur | 448899 | Bahadurpur | 81 | 80 | 99 | Work In Progress | Not Certified | 
| 3 | Basti | Saltaua Gopal Pur | Bahadurpur | 448900 | Pipara Raheem | 69 | 65 | 94 | Work In Progress | Not Certified |