Scheme Details
DISTRICT Barabanki
AGENCY PNC-SPML-JV
SCHEME ID 20037969
SCHEME NAME Tai Kalan Water Supply Scheme
ESTIMATED COST 302.94
EXPENDITURE 190.13
AUTOMATION STATUS
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 10948.00 Meter
Length Laid 10658.00 Meter

Scheme Assigned Villages

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Barabanki Dewa Tai Kalan 435125 Tai Kalan 261 260 100% Work In Progress Not Certified
2 Barabanki Dewa Tai Kalan 435126 Meerpur 132 131 99% Work In Progress Not Certified