Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Barabanki
AGENCY PNC-SPML-JV
SCHEME ID 20037975
SCHEME NAME Avawa & Khandsara Warer Supply Scheme
ESTIMATED COST 314.79
EXPENDITURE 104.14
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 11152.00 Meter
Length Laid 11152.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Barabanki Nindaura Amawa 434504 Avawa 251 245 98% Work In Progress Not Certified
2 Barabanki Nindaura Khandsara 434505 Khandsara 214 206 96% Work In Progress Not Certified