Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20038479 | Daultabad-Dindarpur Gram Panchayat Water Supply | 318.23 | 206.89 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 10684.00 | 10490.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Budhanpur | Dildarpur | 387196 | Dildarpur | 139 | 139 | 100 | Har Gar Jal | Not Certified | 
| 2 | Bijnor | Budhanpur | Dildarpur | 387197 | Gurdadpur Hira | 59 | 47 | 80 | Work In Progress | Not Certified | 
| 3 | Bijnor | Budhanpur | Dildarpur | 387198 | Umarpur | 77 | 75 | 97 | Work In Progress | Not Certified | 
| 4 | Bijnor | Budhanpur | Dulatabad | 387234 | Dulatabad | 170 | 170 | 100 | Har Gar Jal | Not Certified | 
| 5 | Bijnor | Budhanpur | Dulatabad | 387235 | Abusaidpur | 4 | 1 | 25 | Work In Progress | Not Certified | 
| 6 | Bijnor | Budhanpur | Dulatabad | 387236 | Mahipatpur Hemraj | 81 | 25 | 31 | Work In Progress | Not Certified |