Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20038517
SCHEME NAME
Mahmudpur Narayan & Maujampur Dayal Gram Panchayat Water Supply
ESTIMATED COST
390.17
EXPENDITURE
302.40
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
44
Procured
45
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9633.00
Meter
Length Laid
8496.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Kotwali | Mahmudpur Nara1an | 386486 | Mahmudpur Nara1an | 424 | 424 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bijnor | Kotwali | Mahmudpur Nara1an | 386487 | Nizampur Padarath | 105 | 87 | 83% | Work In Progress | Not Certified |
| 3 | Bijnor | Kotwali | Maujampur Dayal | 386488 | Maujampur Da1al | 185 | 175 | 95% | Work In Progress | Not Certified |